Current Progress and Next Major Work of Second-Line Carbon Black Project
Phase II carbon black finished product warehouse has been basically completed; the basic works of packaging and granulation plants have been completed; a layer of steel formwork and main bag filter foundation are being constructed; the micron crusher platform and reprocessing foundation have been excavated; the drawings of equipment, electrical appliances and instrumentation have been basically completed; the orders of main equipment have been completed; the site installation and construction units have been determined; the materials of non-standard equipment have been submitted. Purchase; Pre-order operation of electrical appliances.
The next major work: packaging plant, granulation plant, the main project completed; all equipment foundation basically completed; electrical parts ordered; reactor ordered; field equipment production.